Site Prep & Installation

Installation Resources

Everything your site needs before your unit arrives: slab dimensions, electrical service, and fuel supply. Get these right and your incinerator burns right from day one.

Concrete Slab

Minimum recommended slab sizes

Pour a concrete foundation with 2–3 feet of extra slab on each side of the unit. Slabs should be poured at least 6 inches thick and dead level — level is critical for a proper burn.

ModelRecommended Slab
ECO-2508′ × 10′ · 6″ thick
ECO-50010′ × 10′ · 6″ thick
ECO-75010′ × 12′ · 6″ thick
ECO-100010′ × 12′ · 6″ thick
ECO-150012′ × 16′ · 6″ thick
ECO-200014′ × 16′ · 6″ thick
ECO-300014′ × 16′ · 6″ thick
Utilities

Electrical & fuel service

Electrical

Standard 110 volt, 60Hz, 20 amp service — every model, no exceptions. No three-phase or specialty electrical work required.

Fuel Options

Every unit is configured at the factory for the fuel you have on site: diesel, propane gas, or natural gas.

Questions on safety, operation & servicing?

If you have any questions about safety, operation, servicing, or warranty coverage, don't hesitate to contact the factory at +1 (229) 439-4874 or info@ecoconcepts.org.

Site prepped? Time to spec your unit.